Publicação:
Lot sizing and furnace scheduling in small foundries

dc.contributor.authorAraujo, Silvio A. de
dc.contributor.authorArenales, Marcos N.
dc.contributor.authorClark, Alistair R.
dc.contributor.institutionUniversidade Estadual Paulista (Unesp)
dc.contributor.institutionUniversidade de São Paulo (USP)
dc.contributor.institutionUniversity of the West of England
dc.date.accessioned2014-05-27T11:22:48Z
dc.date.available2014-05-27T11:22:48Z
dc.date.issued2008-03-01
dc.description.abstractA lot sizing and scheduling problem prevalent in small market-driven foundries is studied. There are two related decision levels: (1) the furnace scheduling of metal alloy production, and (2) moulding machine planning which specifies the type and size of production lots. A mixed integer programming (MIP) formulation of the problem is proposed, but is impractical to solve in reasonable computing time for non-small instances. As a result, a faster relax-and-fix (RF) approach is developed that can also be used on a rolling horizon basis where only immediate-term schedules are implemented. As well as a MIP method to solve the basic RF approach, three variants of a local search method are also developed and tested using instances based on the literature. Finally, foundry-based tests with a real-order book resulted in a very substantial reduction of delivery delays and finished inventory, better use of capacity, and much faster schedule definition compared to the foundry's own practice. © 2006 Elsevier Ltd. All rights reserved.en
dc.description.affiliationInstituto de Biociências Letras e Ciências Exatas Departamento de Ciências da Computação e Estatística, Sao Jose do Rio Preto, SP 15054-000
dc.description.affiliationInstituto de Ciências Matemáticas e de Computação Departamento de Matemática Aplicada e Estatística Universidade de São Paulo, Caixa Postal 668, São Carlos, SP 13560-970
dc.description.affiliationFaculty of Computing Engineering and Mathematical Sciences University of the West of England, Bristol, BS16 1QY
dc.format.extent916-932
dc.identifierhttp://dx.doi.org/10.1016/j.cor.2006.05.010
dc.identifier.citationComputers and Operations Research, v. 35, n. 3, p. 916-932, 2008.
dc.identifier.doi10.1016/j.cor.2006.05.010
dc.identifier.issn0305-0548
dc.identifier.orcid0000-0002-4762-2048
dc.identifier.scopus2-s2.0-34548453509
dc.identifier.urihttp://hdl.handle.net/11449/70313
dc.identifier.wosWOS:000250256100022
dc.language.isoeng
dc.relation.ispartofComputers and Operations Research
dc.relation.ispartofjcr2.962
dc.relation.ispartofsjr1,916
dc.rights.accessRightsAcesso restrito
dc.sourceScopus
dc.subjectLot sizing and scheduling
dc.subjectMeta-heuristics
dc.subjectMixed integer programming
dc.subjectHeuristic algorithms
dc.subjectInteger programming
dc.subjectMetadata
dc.subjectProblem solving
dc.subjectTabu search
dc.subjectMetaheuristics
dc.subjectScheduling
dc.titleLot sizing and furnace scheduling in small foundriesen
dc.typeArtigo
dcterms.licensehttp://www.elsevier.com/about/open-access/open-access-policies/article-posting-policy
dspace.entity.typePublication
unesp.author.orcid0000-0002-4762-2048[1]
unesp.campusUniversidade Estadual Paulista (UNESP), Instituto de Biociências Letras e Ciências Exatas, São José do Rio Pretopt
unesp.departmentCiências da Computação e Estatística - IBILCEpt

Arquivos