EPB excavation in transitional mixed face: Line 5—Lilac (São Paulo Metro, Brazil)

dc.contributor.authorFilho, Luís Cesar Esteves Flamínio [UNESP]
dc.contributor.authorHartwig, Marcos Eduardo
dc.contributor.authorMoreira, Cesar Augusto [UNESP]
dc.contributor.institutionUniversidade Estadual Paulista (UNESP)
dc.contributor.institutionAlto Universitário
dc.date.accessioned2023-03-01T19:53:18Z
dc.date.available2023-03-01T19:53:18Z
dc.date.issued2022-05-01
dc.description.abstractThe use of Earth Pressure Balance (EPB) shields is still very modest for tunneling in urban areas in Brazil. This study analyzed and integrated geological data and excavation parameters of a segment of Route 2 (Lot 3) of the Line 5—Lilac (São Paulo Metro), between Campo Belo Station and Jesuíno Maciel Shaft. This segment is 557 m long and represents one of the first experiences on tunneling in transitional mixed face with pressurized shield machines in Brazil. The excavation performed an average advance rate of 7.7 m/day and intercepted different proportions of gneisses, saprolites, and residual soils. The results show how the excavation parameters respond to different geological materials. The sections excavated in mixed transitional ground conditions had several negative effects on the excavation process, similarly to that described in other projects worldwide. Finally, results also suggested the nominal torque was insufficient for excavation of the segment.en
dc.description.affiliationSão Paulo State University (Geosciences and Environmental Graduate Program), 24-A Avenue
dc.description.affiliationDepartment of Geology Federal University of Espírito Santo Alto Universitário, Guararema
dc.description.affiliationUnespSão Paulo State University (Geosciences and Environmental Graduate Program), 24-A Avenue
dc.identifierhttp://dx.doi.org/10.1007/s10064-022-02694-z
dc.identifier.citationBulletin of Engineering Geology and the Environment, v. 81, n. 5, 2022.
dc.identifier.doi10.1007/s10064-022-02694-z
dc.identifier.issn1435-9537
dc.identifier.issn1435-9529
dc.identifier.scopus2-s2.0-85128616345
dc.identifier.urihttp://hdl.handle.net/11449/239919
dc.language.isoeng
dc.relation.ispartofBulletin of Engineering Geology and the Environment
dc.sourceScopus
dc.subjectEPB
dc.subjectExcavation parameters
dc.subjectLithological profile
dc.subjectMixed face
dc.subjectTBM
dc.titleEPB excavation in transitional mixed face: Line 5—Lilac (São Paulo Metro, Brazil)en